Crews are currently engaged in striping state highways across Wallowa County, a process expected to continue until July 3, 2024

Wallowa, OR – According to the ODOT officials, the work is planned to proceed in the following sequence, with each highway anticipated to require two to three days for completion:
- OR 3 (Enterprise-Lewiston Highway): Striping will commence from the Oregon/Washington state line (milepost 0) and proceed southward to Enterprise (milepost 43).
- OR 82 (Wallowa Lake Highway): Striping operations will start in Elgin (milepost 20) and extend eastward to Joseph (milepost 72).
- OR 350 (Little Sheep Creek Highway): Crews will begin striping from Joseph (milepost 0) and continue eastward to Imnaha (milepost 27).
The schedule for this work is contingent on weather conditions and is subject to adjustment as necessary to ensure optimal completion.
Motorists are advised to exercise caution and observe signage and crew instructions while traveling through these areas during the striping operations.
-
Oregon1 week ago“This is another Trumpian attack on children,” Oregon Sen. Merkley accuses Trump administration of taking away attorneys for unaccompanied children to make deportations easier
-
Eugene1 week agoEugene-Springfield Fire responds to structure fire that damaged home, shed and power pole
-
Eugene1 week agoEugene Police motorcycle officers train with agencies across Oregon for motorcade operations
-
Eugene1 week agoEugene-Springfield Fire responds to apartment fire that seriously injured one resident near downtown Eugene
-
Eugene1 week agoEugene Police Department thanks local community after National Night Out event
-
Eugene5 hours agoEugene police find missing woman deceased after search involving multiple teams
-
Eugene5 hours agoEugene Springfield Fire responds to grass fire involving railroad trestle along Highway 99
-
Eugene5 hours agoBrush fire behind Eugene’s Franklin Boulevard prompts multi-unit fire response near railroad tracks