The intersection of Foothill Road and Hillcrest Road will have traffic impacts from Wednesday, July 5 through Tuesday, July 18 from 7:00 a.m. to 5:00 p.m. while contractors perform water and storm drain work

Medford, OR – According to the statement, Foothill Road will be open, but delays are expected with traffic being flagged through each leg of the intersection.
The work is part of the $62 million Foothill Road project being constructed in part due to a $15 million Federal Build Grant received by Medford.
It improves Foothill Road from Delta Waters Road south to Hillcrest Road.
When complete at the end of 2026, the existing two-lane road will feature two lanes in each direction, along with turn lanes, sidewalks, bike lanes and street lighting.
-
Eugene5 days ago
Firefighters contain South Hills house fire in Eugene, prevent spread to nearby trees and homes
-
Oregon5 days ago
Governor Kotek invokes Emergency Conflagration Act for Elk Fire in Klamath County as wildfire threat grows
-
Eugene3 days ago
19-year-old taken into custody on drug and weapon charges after early morning contact at Skinner Butte Park
-
Eugene5 days ago
Eugene braces for heat advisory as temperatures near 100 degrees, splash pads open daily to help residents stay cool
-
Eugene3 days ago
Propane leak shuts down section of Danebo during emergency response in west Eugene
-
Eugene3 days ago
Eugene firefighters battle three suspicious brush fires in early morning hours along East Bank Bike Path
-
Eugene3 days ago
Dozens begin careers in emergency response as 43 new recruits enter Eugene Springfield Fire EMS academy
-
Eugene1 week ago
34-year-old suspect wanted for murder apprehended by Eugene police using license plate reader system